Before Installation of a Distributed Generation (DG) Facility
A member seeking interconnection of a DG facility to the cooperative system must submit all applicable forms to PHEC for review and approval before beginning installation. Member-owned or leased generator equipment and solar installations must be installed in accordance with the manufacturer’s specifications, as well as all applicable provisions of the national electrical codes (including the National Electrical Code (NEC), the Institute of Electrical and Electronics Engineers (IEEE), the National Electrical Safety Code (NESC), and Underwriters Laboratories (UL)) at the members own expense.
Standard Interconnection Agreement for Louisiana Members
Renewable Energy Application and Contract for Texas Members
The current renewable energy rate paid for excess generation is $.0250 per kWh.
The PHEC renewable energy rate is calculated as the previous calendar twelve-month average Locational Marginal Price (LMP) for the appropriate PHEC load zone.
Please submit the applicable agreement (above) along with specifications and drawings of the installation for review and approval to support@phec.us, or mail to:
Panola-Harrison EC
Attention: DG Application
P.O. Box 1058
Marshall, TX 75670